Renewal of the indoor pool at Sundhöll

Description of the action and objectives

Green Deal action

Plans are underway to renovate the indoor pool's banks and basin of Sundhöll Reykjavík Pool, which are getting old. In addition to this, a special diving pool will be created for the diving boards.

 

Implementation period

Planned completion in the first half of 2026

Status: In progress

Status report on January 1, 2024

Construction should start next fall and will continue throughout 2025 and into part of 2026. Plans include improving the steam bath facilities and adding hot pots on the balconies. The building permit application has been approved.

Older status reports

Timing Progress description
July 2023

Construction was supposed to start this year, but it was postponed due to the City's financial situation. Efforts will begin in spring 2024 to renovate the pool deck and the pool basin in the indoor pool of Sundhöll Pool. The construction is expected to take about one and a half to two years.

January 2023 Alterations have been designed for the Sundhöll indoor pool, but construction has been postponed until fall 2023.
July 2022 Alterations have been designed for the Sundhöll indoor pool, and construction is projected to commence in spring 2023.