Dalslaug is in full operation and a new slide is under construction

Description of the action and objectives

Green Deal action

Plans are underway to renovate the indoor pool's banks and basin of Sundhöll Reykjavík Pool, which are getting old. In addition to this, a special diving pool will be created for the diving boards.

 

Implementation period

Planned completion in the second half of 2023

Status: In progress

Status report on January 1, 2024

Action completed. Dalslaug is now fully operational with two new slides.

Older status reports

Below you can find older status reports with information on the progress of the action since its inception (if you're using your phone, it's better to turn it sideways).
Timing Progress description
July 2023 The installation of a slide is nearing completion, aiming to be ready for use around the end of September/October 2023. Plans are in place to start building a new watchtower by the turn of the year 2023/2024.
January 2023 Construction on the slide is underway, with completion anticipated by the end of summer 2023.
July 2022 A new slide has been designed and open for bids, and construction will begin in early 2023. The project is expected to be finished by fall 2023.