Checklist of confirmation documents
Below is a checklist of documents you might need to submit and from whom you can retrieve them. Not all documents are required for every inspection, only those that apply.
Construction manager
- Confirmation from the construction manager that all mandatory inspections are recorded in HMS's construction portal.
- The house manual according to HMS's Guidelines No. 16.1.1.
- A statement from the person who installed the waterproof systems of tiled bathtubs and shower enclosures and a work description for the waterproof system.
Fire safety
- Memorandum from fire safety designer approved by the fire department.
- Statement on a complete and tested fire alarm system
- Documents for the operator's self-inspection as required by Regulation No 200/1994 and guidelines on the fire department's website.
- Most recent inspection report of the fire alarm system. The report must be less than one year old. If it is not, a new inspection and report are required.
- Service contract for the inspection and maintenance of the fire alarm system.
- Service contract for the connection and monitoring of the fire alarm system.
- Statement on a complete sprinkler system in the kitchen hood
- Service contract for the inspection and maintenance of the kitchen hood sprinkler system.
- Inspection report on the kitchen hood sprinkler system.
- Confirmation that the elevator doors meet fire safety requirements.
- Confirmation of the installation, testing, and activity of fire curtains.
- Service contract for the inspection and maintenance of fire curtains.
- Confirmation that the fire curtain meets design requirements.
- Confirmation from those who performed fire sealings.
- Operating permit of those who performed fire sealings.
Ventilation
- Statement on the setting and testing of the interoperability of equipment and the measurement of air quantity and distribution
- Adjustment reports for the ventilation system.
Piping system
- Service contract for the inspection and maintenance of the water sprinkler system.
- Inspection report of the water sprinkler system (acceptance test).
- Statement on a complete water sprinkler system
- Statement that the water sprinkler system has been notified to the fire department.
- Statement on the setting of the heating system and activity of control devices for safety or final inspection
- Statement on the testing of gas pipelines
- Statement on pressure testing and inspection of riser pipes, HMS 9.8.5 guidelines.
- Statement that hot tap water in sinks and showers will never be hotter than specified in Article 14.5.10 of Building Regulation 112/2012. Temperature in main pipelines should be 65°C, and mixing to 38°C or 43°C should occur at the tap as applicable.
Electrical installations
- Statement on the completion of electrical installations for safety or final inspection
- Statement on the testing and activity of emergency lighting and exit signs, HMS 9.4.12 guidelines
- Statement on the testing and activity of sliding doors on escape routes and service contract for inspection and maintenance.
- Statement on the testing and activity of smoke extraction and service contract.
Elevators
- Statement from The Administration of Occupational Safety and Health on the final inspection of the elevator.
- Service contract for the inspection and maintenance of the elevator.
Operator
- Response plan / training plan for operators.